PSM-II · Question #22
Your organization has formed a new Scrum Team and has assigned you as the Scrum Master. In what ways would you help the team start?
The correct answer is B. Have the Scrum Team members introduce their background experience with each other, ask the. Scrum Teams should have all of the competencies and skills to do the work in the Product Backlog which includes understanding the goals and history of the product and ensuring that they all know what "done" means.
Dealing with People and Teams
Question
Your organization has formed a new Scrum Team and has assigned you as the Scrum Master. In what ways would you help the team start?
Options
- AEnsure the Scrum Team members have compatible personalities, have the tech leads clarify the
- BHave the Scrum Team members introduce their background experience with each other, ask the
How the community answered
(41 responses)- A7% (3)
- B93% (38)
Explanation
Scrum Teams should have all of the competencies and skills to do the work in the Product Backlog which includes understanding the goals and history of the product and ensuring that they all know what "done" means.
Topics
#team formation#onboarding#team dynamics#Scrum Team