PSM-II · Question #23

What guideline should the Scrum Master provide if the Product Owner asks how estimations should be made in Scrum?

The correct answer is C. The Development Team is responsible for estimates. The people who will perform the work make the final estimates.

Applying Scrum

Question

What guideline should the Scrum Master provide if the Product Owner asks how estimations should be made in Scrum?

Options

  • AEstimates must be made in Story Points.
  • BEstimates must be in relative units.
  • CThe Development Team is responsible for estimates.
  • DEstimates are made by the Product Owner.
  • EEstimates must follow the Fibonacci Sequence.

How the community answered

(50 responses)
  • A
    2% (1)
  • B
    6% (3)
  • C
    90% (45)
  • D
    2% (1)

Explanation

The people who will perform the work make the final estimates.

Topics

#estimation#Development Team responsibility#Scrum roles#Product Owner