Who must ensure that the work done for a Product Backlog item conforms to the Definition of "Done?"
The correct answer is E. The Development Team. The Development Team owns the Definition of "Done" and is accountable for the quality of the Product Backlog items.
Applying Scrum
Question
Who must ensure that the work done for a Product Backlog item conforms to the Definition of "Done?"
Options
- AThe test team.
- BThe Scrum Team.
- CThe Scrum Master.
- DThe Product Owner.
- EThe Development Team.
How the community answered
(18 responses)- A6% (1)
- B6% (1)
- E89% (16)
Explanation
The Development Team owns the Definition of "Done" and is accountable for the quality of the Product Backlog items.
Topics
#Definition of Done#Development Team#quality accountability