Which statement is FALSE in regards to the Sprint Goal?

Sign in or unlock PSM-II to reveal the answer and full explanation for question #29. The question stem and answer options stay visible for context.

Applying Scrum

Question

Which statement is FALSE in regards to the Sprint Goal?

Options

  • AIt is only a forecast and changes during the Sprint as more is learned.
  • BIf it doesn't seem achievable, the Development Team has the courage to tell the Product Owner.
  • CThe Product Owner respects the Development Team's opinion on whether they can achieve it.
  • DIt helps increase focus.
  • EThe Scrum Team discusses openly about alternative ways to reach it.
  • FThe Development Team commits to it.

Unlock PSM-II to see the answer

You've previewed enough free PSM-II questions. Unlock PSM-II for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Sprint Goal#commitment#forecast#Sprint Planning
Full PSM-II Practice