Question
A Scrum Master is not only a servant-leader to the Scrum Team and organization, it's also considered a management position. Which three activities describe what a Scrum Master manages as reflected by the Scrum Guide? (Choose three.)
Options
- AReporting on the performance of the Sprint.
- BThe way Scrum is understood and enacted within the organization.
- CManaging the capacity and utilization of each Development Team member.
- DManaging the process in which Scrum is applied.
- EManaging the Product Backlog items and work in the Sprint Backlog.
- FRemoving organizational impediments that limits the team's progress and productivity.