PSM-II · Question #111

The Sprint length should be:

The correct answer is D. All of these answers are correct. Option D is correct because the Scrum Guide defines Sprint length constraints using all three criteria simultaneously - none of them alone is the complete rule. A Sprint must be short enough to limit business risk (A), short enough to stay synchronized with business events (B)…

Applying Scrum

Question

The Sprint length should be:

Options

  • AShort enough to keep the business risk acceptable to the Product Owner.
  • BShort enough to be able to synchronize the development work with other business events.
  • CNo more than one month.
  • DAll of these answers are correct.

How the community answered

(51 responses)
  • A
    2% (1)
  • B
    2% (1)
  • C
    4% (2)
  • D
    92% (47)

Explanation

Option D is correct because the Scrum Guide defines Sprint length constraints using all three criteria simultaneously - none of them alone is the complete rule. A Sprint must be short enough to limit business risk (A), short enough to stay synchronized with business events (B), and capped at a maximum of one month (C); the official guidance combines all three as co-equal constraints on Sprint duration.

There are no "distractors" here - A, B, and C are each individually true statements drawn directly from Scrum's definition of a Sprint, which is why D ("all of the above") is the only complete answer.

Memory tip: Think of Sprint length as a three-legged stool - risk control, business synchronization, and the one-month hard cap. Remove any leg and the stool (and your exam answer) falls over. When you see all three listed as separate choices alongside "all of the above," that's a signal the Scrum Guide treats them as a unified definition, not competing options.

Topics

#Sprint length#business risk#time-boxing#synchronization