PSM-II · Question #110
How should a Scrum Master respond if the Product Owner plans the first Sprint to only focus on setting up the infrastructure and architecture in order to work on functionality in a subsequent Sprint?
The correct answer is A. Help the Product Owner understand the value of including business functionality into every Sprint. Getting feedback from the Users and Stakeholders is a crucial activity in Scrum. It reduces waste from building items that add no value. Saying that, the best architectures, requirements, and designs emerge from self-organizing teams.
Question
How should a Scrum Master respond if the Product Owner plans the first Sprint to only focus on setting up the infrastructure and architecture in order to work on functionality in a subsequent Sprint?
Options
- AHelp the Product Owner understand the value of including business functionality into every Sprint
- BSupport the Product Owner's decision as he/she is accountable for maximizing the value of the
- CExplain that one Sprint may be too short to finish the architecture and he should pre-allocate
- DAdd at least one technical architect to the Development Team to ensure the architecture can be
How the community answered
(48 responses)- A73% (35)
- B15% (7)
- C4% (2)
- D8% (4)
Explanation
Getting feedback from the Users and Stakeholders is a crucial activity in Scrum. It reduces waste from building items that add no value. Saying that, the best architectures, requirements, and designs emerge from self-organizing teams.