What must the Development Team do during the first Sprint?
The correct answer is A. Create a potentially shippable product Increment that includes at least one piece of functionality. Sprints promote iterative and incremental development.
Applying Scrum
Question
What must the Development Team do during the first Sprint?
Options
- ACreate a potentially shippable product Increment that includes at least one piece of functionality.
- BAnalyze and estimate the requirements for the subsequent Sprints.
- CCreate a project plan in order to map functional development to Sprint dates.
- DOnly design and develop the architecture and infrastructure.
How the community answered
(35 responses)- A86% (30)
- B6% (2)
- C6% (2)
- D3% (1)
Explanation
Sprints promote iterative and incremental development.