PSM-II · Question #108

Who can prematurely cancel a Sprint?

The correct answer is B. The Product Owner. Only the Product Owner can determine when items being worked on are obsolete.

Applying Scrum

Question

Who can prematurely cancel a Sprint?

Options

  • AThe Development Team
  • BThe Product Owner
  • CThe Stakeholders
  • DThe Scrum Master

How the community answered

(26 responses)
  • B
    96% (25)
  • C
    4% (1)

Explanation

Only the Product Owner can determine when items being worked on are obsolete.

Topics

#Sprint cancellation#Product Owner authority#accountability#Scrum roles