Who can prematurely cancel a Sprint?
The correct answer is B. The Product Owner. Only the Product Owner can determine when items being worked on are obsolete.
Applying Scrum
Question
Who can prematurely cancel a Sprint?
Options
- AThe Development Team
- BThe Product Owner
- CThe Stakeholders
- DThe Scrum Master
How the community answered
(26 responses)- B96% (25)
- C4% (1)
Explanation
Only the Product Owner can determine when items being worked on are obsolete.