nerdexam
Scrum

PSM-II · Question #169

After several Sprints, a key stakeholder starts using the product. The stakeholder is surprised by the slow performance and complains to the Product Owner. The Product Owner comes to the Scrum…

The correct answer is D. Encourage the Product Owner to bring the performance concerns to the Development Team and. The highest priority of agility is to satisfy the customer through early and continuous delivery of valuable software. Because the Development Team is the one doing the work and increments must meet performance standards, they can expand their Definition of Done to include more…

Coaching & Mentoring

Question

After several Sprints, a key stakeholder starts using the product. The stakeholder is surprised by the slow performance and complains to the Product Owner. The Product Owner comes to the Scrum Master asking for advice. What is the best action for a Scrum Master to take?

Options

  • AWait until the next Sprint Retrospective as it is the most opportune time to modify the Definition of
  • BBring the concern to the testers in the Development Team and ask them to include performance
  • CExplain to the Product Owner that it's up to the Development Team to. decide on acceptable
  • DEncourage the Product Owner to bring the performance concerns to the Development Team and

How the community answered

(46 responses)
  • A
    11% (5)
  • B
    2% (1)
  • C
    4% (2)
  • D
    83% (38)

Explanation

The highest priority of agility is to satisfy the customer through early and continuous delivery of valuable software. Because the Development Team is the one doing the work and increments must meet performance standards, they can expand their Definition of Done to include more stringent criteria for higher quality.

Topics

#Definition of Done#performance#stakeholder feedback#technical quality