Question
Scrum addresses which of the following four risks in software development? (Choose four.)
Options
- AThe complexity and unpredictability of the requirements.
- BThe stability and complexity of the technology.
- CThe skills and working relationships of the people on the teams.
- DThe timescale of the planned work.
- EThe clear definitions of stages and gateways in the overall governance model.
- FThe definition of incentive and bonus strategies by HR for all team members.