Question

Scrum addresses which of the following four risks in software development? (Choose four.)

Options

  • AThe complexity and unpredictability of the requirements.
  • BThe stability and complexity of the technology.
  • CThe skills and working relationships of the people on the teams.
  • DThe timescale of the planned work.
  • EThe clear definitions of stages and gateways in the overall governance model.
  • FThe definition of incentive and bonus strategies by HR for all team members.