nerdexam
Scrum

PSM-II · Question #167

PSM-II Question #167: Real Exam Question with Answer & Explanation

The correct answer is B. It's also incorrect for the PO to focus on completing the entire Sprint Backlog. Finishing. Scrum is founded on empirical process control theory, or empiricism. Empiricism asserts that knowledge comes from experience and making decisions based on what is known. The Sprint Backlog is a forecast by the Development Team about what functionality will be in the next Incremen

Question

Steven is a Scrum Master of a Scrum Team that is new to Scrum. At the halfway point of the Sprint, the Product Owner comes to Steven telling him that he is concerned the Development Team will not be able to complete the entire Sprint Backlog by the end of the Sprint. What should Steven do in this situation?

Options

  • AThe Dev Team does not commit to finishing all items in the Sprint Backlog. Committing to
  • BIt's also incorrect for the PO to focus on completing the entire Sprint Backlog. Finishing
  • CAdvise the Product Owner that the Development Team owns the Sprint Backlog and it is up to
  • DAdd more people to the Development Team to meet the Product Owner's expectations.

Explanation

Scrum is founded on empirical process control theory, or empiricism. Empiricism asserts that knowledge comes from experience and making decisions based on what is known. The Sprint Backlog is a forecast by the Development Team about what functionality will be in the next Increment and the work needed to deliver that functionality into a `Done' Increment. The Development Team modifies the Sprint Backlog throughout the Sprint, and the Sprint Backlog emerges during the Sprint. This emergence occurs as the Development Team works through the plan and learns more about the work needed to achieve the Sprint Goal. Why C is incorrect: completing all items would be fixed scope and fixed time leaving no room to adapt. They commit to the Sprint Goal and doing the right thing. everything should not be his main focus. Having a shippable increment that meets the Sprint Goal is more important than trying to finish everything. The advice in option C is equivalent to "Don't worry, they'll get everything done." but because of the complex domain, you cannot guarantee everything will get done.

Community Discussion

No community discussion yet for this question.

Full PSM-II Practice