PSM-II · Question #93
A key concern when multiple Development Teams are working for the same Product Backlog is minimizing dependencies between teams.
The correct answer is A. True. Minimizing dependencies reduces complexity and enhances agility.
Scaling Scrum
Question
A key concern when multiple Development Teams are working for the same Product Backlog is minimizing dependencies between teams.
Options
- ATrue
- BFalse
How the community answered
(34 responses)- A91% (31)
- B9% (3)
Explanation
Minimizing dependencies reduces complexity and enhances agility.
Topics
#multiple teams#inter-team dependencies#Product Backlog#coordination