Scrum
PSM-II · Question #11
PSM-II Question #11: Real Exam Question with Answer & Explanation
The correct answer is B. False. If there are multiple Scrum Teams working on the system or product release, the Development Teams on all the Scrum Teams must mutually define the definition of "Done". Each Increment is additive to all prior Increments and thoroughly tested, ensuring that all Increments work toge
Question
During the Sprint Review of a scaled development effort, each Scrum Team should demonstrate its individual Increment in a separate branch of the code.
Options
- ATrue
- BFalse
Explanation
If there are multiple Scrum Teams working on the system or product release, the Development Teams on all the Scrum Teams must mutually define the definition of "Done". Each Increment is additive to all prior Increments and thoroughly tested, ensuring that all Increments work together.
Community Discussion
No community discussion yet for this question.