PSM-II · Question #11

During the Sprint Review of a scaled development effort, each Scrum Team should demonstrate its individual Increment in a separate branch of the code.

The correct answer is B. False. If there are multiple Scrum Teams working on the system or product release, the Development Teams on all the Scrum Teams must mutually define the definition of "Done". Each Increment is additive to all prior Increments and thoroughly tested, ensuring that all Increments work…

Scaling Scrum

Question

During the Sprint Review of a scaled development effort, each Scrum Team should demonstrate its individual Increment in a separate branch of the code.

Options

  • ATrue
  • BFalse

How the community answered

(40 responses)
  • A
    15% (6)
  • B
    85% (34)

Explanation

If there are multiple Scrum Teams working on the system or product release, the Development Teams on all the Scrum Teams must mutually define the definition of "Done". Each Increment is additive to all prior Increments and thoroughly tested, ensuring that all Increments work together.

Topics

#Sprint Review#scaling#integrated Increment#branching