PSM-II · Question #125
Three Development Teams are currently building a single product and pulling work from the same Product Backlog. All three teams have identified that they will need Dan, a database specialist, to…
The correct answer is C. Facilitate a discussion with all Development Teams on how they want to deal with this issue, and. As a servant/leader, the Scrum Master facilitates conversations through open ended questions in order to help the team members make the best possible decisions according to what is known at the time. He/she does not approve or reject team decisions but ensures the team stays…
Question
Three Development Teams are currently building a single product and pulling work from the same Product Backlog. All three teams have identified that they will need Dan, a database specialist, to work full time in their team for the next several Sprints. What should Steven, the Scrum Master, do to solve this potential problem?
Options
- AManage the items in the Sprint Backlogs so that Dan can be utilized evenly for each team.
- BAssign Dan to the team with the most urgent tasks first and then move him to the next team and
- CFacilitate a discussion with all Development Teams on how they want to deal with this issue, and
- DAsk Dan to work with the HR department to recruit and hire additional database specialists. In the
How the community answered
(25 responses)- A12% (3)
- B4% (1)
- C80% (20)
- D4% (1)
Explanation
As a servant/leader, the Scrum Master facilitates conversations through open ended questions in order to help the team members make the best possible decisions according to what is known at the time. He/she does not approve or reject team decisions but ensures the team stays within the boundaries of the Scrum framework.