PSM-II · Question #91
Who should manage the tasks of Development Team during the Sprint?
The correct answer is D. The Development Team. The Development Team is responsible for managing and tracking the progress of their work
Applying Scrum
Question
Who should manage the tasks of Development Team during the Sprint?
Options
- AThe Project Manager.
- BThe Product Owner.
- CThe Scrum Master.
- DThe Development Team.
- EAll of the above.
How the community answered
(28 responses)- A4% (1)
- B4% (1)
- D86% (24)
- E7% (2)
Explanation
The Development Team is responsible for managing and tracking the progress of their work
Topics
#self-management#Sprint#Development Team#task ownership