PSM-II · Question #91

Who should manage the tasks of Development Team during the Sprint?

The correct answer is D. The Development Team. The Development Team is responsible for managing and tracking the progress of their work

Applying Scrum

Question

Who should manage the tasks of Development Team during the Sprint?

Options

  • AThe Project Manager.
  • BThe Product Owner.
  • CThe Scrum Master.
  • DThe Development Team.
  • EAll of the above.

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    4% (1)
  • D
    86% (24)
  • E
    7% (2)

Explanation

The Development Team is responsible for managing and tracking the progress of their work

Topics

#self-management#Sprint#Development Team#task ownership