PSM-II Question #68: Real Exam Question with Answer & Explanation

The correct answer is B. As needed, while taking into account a short term reduction in productivity.. It is not mandatory that the same team stay together, although it must be understood that any changes to the team will impact how they work together.

Question

How often should Development Team membership change?

Options

  • AFrequently in order to share knowledge.
  • BAs needed, while taking into account a short term reduction in productivity.
  • CNever, as it conflicts with the Scrum process.
  • DAs needed, as long as it doesn't impact productivity.

Explanation

It is not mandatory that the same team stay together, although it must be understood that any changes to the team will impact how they work together.