PSM-II · Question #21

A Scrum Master is keeping a list of open impediments, but it is growing and he/she has been able to resolve only a small portion of the impediments. Which would be the LEAST helpful technique in…

The correct answer is C. Arranging a triage meeting with all project managers. Scrum does not have project managers and arranging a triage meeting would not help accelerate the removal of impediments.

Solving Problems

Question

A Scrum Master is keeping a list of open impediments, but it is growing and he/she has been able to resolve only a small portion of the impediments. Which would be the LEAST helpful technique in this situation?

Options

  • AConsulting with the Development Team
  • BPrioritizing the list and working on them in order.
  • CArranging a triage meeting with all project managers.
  • DAlerting management to the impediments and their impact.

How the community answered

(27 responses)
  • A
    11% (3)
  • B
    7% (2)
  • C
    78% (21)
  • D
    4% (1)

Explanation

Scrum does not have project managers and arranging a triage meeting would not help accelerate the removal of impediments.

Topics

#impediment management#prioritization#escalation#Scrum Master role