The correct answer is C. Arranging a triage meeting with all project managers.. Scrum does not have project managers and arranging a triage meeting would not help accelerate the removal of impediments.
Question
A Scrum Master is keeping a list of open impediments, but it is growing and he/she has been able to resolve only a small portion of the impediments. Which would be the LEAST helpful technique in this situation?
Options
- AConsulting with the Development Team
- BPrioritizing the list and working on them in order.
- CArranging a triage meeting with all project managers.
- DAlerting management to the impediments and their impact.
Explanation
Scrum does not have project managers and arranging a triage meeting would not help accelerate the removal of impediments.