PSM-II · Question #164

At the fifth Sprint Retrospective, the Product Owner mentions that he is surprised about the amount of technical debt that has built up in the system and that the product is not able to support an…

The correct answer is E. All of the above. Each component within the Scrum framework serves a specific purpose and is essential to Scrum's success and usage. Scrum's roles, events, artifacts, and rules are immutable and although implementing only parts of Scrum is possible, the result is not Scrum.

Solving Problems

Question

At the fifth Sprint Retrospective, the Product Owner mentions that he is surprised about the amount of technical debt that has built up in the system and that the product is not able to support an adequate number of users. Peter, the Product Owner, is upset that the product will need several more Sprints to address the scalability issues in order to meet his expectations. What factors may have led to this?

Options

  • AThe Scrum Team has not used the past Sprint Retrospectives effectively to inspect and adapt.
  • BThe Development Team has not been paying enough attention to technical quality.
  • CThe Development Team and the Product Owner are not having conversations around technical
  • DThe Scrum Master has not ensured that the Scrum Team is transparent.
  • EAll of the above.
  • FNone of the above.

How the community answered

(45 responses)
  • A
    2% (1)
  • B
    2% (1)
  • C
    4% (2)
  • D
    16% (7)
  • E
    69% (31)
  • F
    7% (3)

Explanation

Each component within the Scrum framework serves a specific purpose and is essential to Scrum's success and usage. Scrum's roles, events, artifacts, and rules are immutable and although implementing only parts of Scrum is possible, the result is not Scrum.

Topics

#technical debt#Sprint Retrospective#transparency#communication