Which two scenarios would best represent a self-organizing Development Team? (Choose two.)

The correct answer is C. Development Team members collaboratively select and re-plan their work throughout the Sprint. E. The Development Team creates its own Sprint Backlog, reflecting all work that is part of the. A self-organized team is a team that is able to self-manage and decide how best to accomplish

Dealing with People and Teams

Question

Which two scenarios would best represent a self-organizing Development Team? (Choose two.)

Options

  • AThe Development Team members are strictly focused on the work within their functional role and
  • BManagement works with the Scrum Master to optimize the Development Team's progress during
  • CDevelopment Team members collaboratively select and re-plan their work throughout the Sprint.
  • DThe Development Team invites external people to the Sprint Planning to help them create a
  • EThe Development Team creates its own Sprint Backlog, reflecting all work that is part of the

How the community answered

(47 responses)
  • B
    4% (2)
  • C
    89% (42)
  • D
    6% (3)

Explanation

A self-organized team is a team that is able to self-manage and decide how best to accomplish

Topics

#self-organization#Sprint Backlog#team collaboration#Development Team