Which three statements best describe the purpose of having a Definition of Done? (Choose three.)
Options
- AIt is a checklist to monitor the Development Team member's progress on a task.
- BIt provides guidance to the Development Team when they are forecasting their Sprint Backlog
- CAs the Development Team is doing the work, it provides guidance on the remaining work needed
- DIt helps the Development Team defer any pending work to subsequent Sprints.
- EIt creates transparency and provides a common understanding of the `done' state of the
- FIt helps the Scrum Team decide how much time is needed before the Sprint can end.