PSM-II · Question #135

Which three statements best describe the purpose of having a Definition of Done? (Choose three.)

The correct answer is B. It provides guidance to the Development Team when they are forecasting their Sprint Backlog C. As the Development Team is doing the work, it provides guidance on the remaining work needed E. It creates transparency and provides a common understanding of the `done' state of the. When a Product Backlog item or an Increment is described as Done', everyone must understand what Done' means. Scrum Team members must have a shared understanding of what it means for work to be complete, to ensure transparency and is used to assess when work is complete on the…

Applying Scrum

Question

Which three statements best describe the purpose of having a Definition of Done? (Choose three.)

Options

  • AIt is a checklist to monitor the Development Team member's progress on a task.
  • BIt provides guidance to the Development Team when they are forecasting their Sprint Backlog
  • CAs the Development Team is doing the work, it provides guidance on the remaining work needed
  • DIt helps the Development Team defer any pending work to subsequent Sprints.
  • EIt creates transparency and provides a common understanding of the `done' state of the
  • FIt helps the Scrum Team decide how much time is needed before the Sprint can end.

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    90% (19)
  • F
    5% (1)

Explanation

When a Product Backlog item or an Increment is described as Done', everyone must understand what Done' means. Scrum Team members must have a shared understanding of what it means for work to be complete, to ensure transparency and is used to assess when work is complete on the product Increment. This Definition of Done provides the team guidance on what it takes to make the increment

Topics

#Definition of Done#Sprint forecasting#transparency#Increment quality

Community Discussion

No community discussion yet for this question.