PSM-II · Question #122

PSM-II Question #122: Real Exam Question with Answer & Explanation

Sign in or unlock PSM-II to reveal the answer and full explanation for question #122. The question stem and answer options stay visible for context.

Question

Paul, a Product Owner of one of the Scrum Teams, has been attending the Daily Scrum. During the Daily Scrum, the Development Team members have been reporting their daily work to Paul so that he is aware of their Sprint progress and what each member is working on. What is the best action for the Scrum Master to take?

Options

  • AAsk Paul to stop attending the Daily Scrum.
  • BCoach Paul and Development Team members on the purpose of the Scrum events and let them
  • CAllow the Paul to participate in the Daily Scrum as he is responsible for the success of the
  • DFacilitate the Daily Scrums to avoid any conflicts between the Development Team members and