nerdexam
Scrum

PSM-II · Question #123

Steven, the Scrum Master, is approached by one of the Development Team members saying that they are not completing regression tests for all of the work they are performing to the level defined in…

The correct answer is C. Ask the Development Team and the Product Owner what problem they are trying to solve by D. Ask the Development Team and the Product Owner if they are still able to produce potentially. As a servant/leader, the Scrum Master facilitates conversations through open ended questions in order to help the team members make the best possible decisions according to what is known at the time. He/she does not approve or reject team decisions but ensures the team stays…

Coaching & Mentoring

Question

Steven, the Scrum Master, is approached by one of the Development Team members saying that they are not completing regression tests for all of the work they are performing to the level defined in the Definition of Done. They have discussed this with the Product Owner and decided to remove regression testing from the Definition of Done. Which two actions are the most appropriate for Steven to take? (Choose two.)

Options

  • AReject the decision as the long term maintainability of the product will be negatively impacted by
  • BAccept the decision as a mutual agreement has been made between the Development Team and
  • CAsk the Development Team and the Product Owner what problem they are trying to solve by
  • DAsk the Development Team and the Product Owner if they are still able to produce potentially

How the community answered

(46 responses)
  • A
    37% (17)
  • B
    17% (8)
  • C
    46% (21)

Explanation

As a servant/leader, the Scrum Master facilitates conversations through open ended questions in order to help the team members make the best possible decisions according to what is known at the time. He/she does not approve or reject team decisions but ensures the team stays within the boundaries of the Scrum framework.

Topics

#Definition of Done#technical debt#quality standards#Scrum Master facilitation

Community Discussion

No community discussion yet for this question.

Full PSM-II Practice