Risk Strategy and Planning

Question

You are the project manager of the NHK Project. Management wants to know how often your risk identification process will occur during the project. Considering that your project is scheduled to last one year and involvs five distinct phases, how often should risk identification take place?

Options

  • AMonthly
  • BOnce per project life cycle phase
  • CQuarterly
  • DVary depending on the situations within the project

Topics

#Risk Identification#Risk Management Process#Iterative Processes#Risk Management Planning

Community Discussion