PMIPMI
PMI-RMP · Question #96
PMI-RMP Question #96: Real Exam Question with Answer & Explanation
The correct answer is D: Vary depending on the situations within the project. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
You are the project manager of the NHK Project. Management wants to know how often your risk identification process will occur during the project. Considering that your project is scheduled to last one year and involvs five distinct phases, how often should risk identification take place?
Options
- AMonthly
- BOnce per project life cycle phase
- CQuarterly
- DVary depending on the situations within the project
Topics
#Risk Identification#Risk Management Process#Iterative Processes#Risk Management Planning
Community Discussion
No community discussion yet for this question.