PMIPMI
PMI-RMP · Question #95
PMI-RMP Question #95: Real Exam Question with Answer & Explanation
The correct answer is B: Assumption. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
Harry is a project manager of a software development project. In the early stages of planning, he and the stakeholders operated with the belief that the software they were developing would work with their organization's current computer operating system. Now that the project team has started developing the software it has become apparent that the software will not work with nearly half of the organization's computer operating systems. The incorrect belief Harry had in the software compatibility is an example of what in project management?
Options
- AIssue
- BAssumption
- CRisk
- DConstraint
Topics
#Assumptions#Risk Identification#Project Planning#Risk Sources
Community Discussion
No community discussion yet for this question.