PMI-RMP · Question #94
You are the project manager for a construction project. The project includes a work that involves very high financial risks. You decide to insure processes so that any ill happening can be…
The correct answer is D. Transfer. Risk Transfer (or Transference) is the correct answer. Insurance is one of the most common forms of risk transference. When you purchase insurance, you are transferring the financial consequences of a risk event to the insurance company (a third party). In exchange for a…
Question
You are the project manager for a construction project. The project includes a work that involves very high financial risks. You decide to insure processes so that any ill happening can be compensated. Which type of strategies have you used to deal with the risks involved with that particular work?
Options
- AMitigate
- BAvoid
- CAccept
- DTransfer
How the community answered
(28 responses)- A7% (2)
- B4% (1)
- C14% (4)
- D75% (21)
Explanation
Risk Transfer (or Transference) is the correct answer. Insurance is one of the most common forms of risk transference. When you purchase insurance, you are transferring the financial consequences of a risk event to the insurance company (a third party). In exchange for a premium, the insurer assumes responsibility for compensating losses if the risk materializes. This does not eliminate the risk itself but shifts the financial burden to another party. Mitigation (A) would involve reducing the likelihood or impact of the risk. Avoidance (B) would require changing the project plan to eliminate the risk entirely. Acceptance (C) means acknowledging the risk and either setting aside a contingency reserve or simply accepting the consequences if it occurs - without shifting responsibility to a third party.
Topics
Community Discussion
No community discussion yet for this question.