nerdexam
PMI

PMI-RMP · Question #97

Della works as a project manager for SoftTech Inc. She is working with the project stakeholders to begin the quantitative risk analysis process. Which of the following inputs will be needed for the…

The correct answer is A. Risk management plan C. Risk register D. Cost management plan. The correct inputs for the Quantitative Risk Analysis process (per PMBOK) are the Risk Management Plan (A), Risk Register (C), and Cost Management Plan (D). The Risk Management Plan defines how risk activities will be conducted, including the approach to quantitative analysis…

Perform Targeted Risk Analysis

Question

Della works as a project manager for SoftTech Inc. She is working with the project stakeholders to begin the quantitative risk analysis process. Which of the following inputs will be needed for the quantitative risk analysis process in her project? Each correct answer represents a complete solution. Choose all that apply.

Options

  • ARisk management plan
  • BProject scope statement
  • CRisk register
  • DCost management plan

How the community answered

(42 responses)
  • A
    90% (38)
  • B
    10% (4)

Explanation

The correct inputs for the Quantitative Risk Analysis process (per PMBOK) are the Risk Management Plan (A), Risk Register (C), and Cost Management Plan (D). The Risk Management Plan defines how risk activities will be conducted, including the approach to quantitative analysis. The Risk Register contains the list of identified risks and results from qualitative analysis that are prioritized for further quantitative analysis. The Cost Management Plan provides the structure and controls for cost estimates, which are critical since quantitative analysis often involves numerical cost and schedule impact modeling (e.g., Monte Carlo simulation, Expected Monetary Value). The Project Scope Statement (B) is an input to the Qualitative Risk Analysis process, not specifically to Quantitative Risk Analysis. Additional standard inputs include the Schedule Management Plan and organizational process assets.

Topics

#Quantitative Risk Analysis#Risk Management Process#Process Inputs#Project Management Plan

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice