nerdexam
PMIPMI

PMI-RMP · Question #84

PMI-RMP Question #84: Real Exam Question with Answer & Explanation

The correct answer is D: Risks. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

Your organization has a project that is expected to last 20 months but the customer would really like the project completed in 18 months. You have worked on similar projects in the past and believe that you could fast track the project and reach the 18 month deadline. What increases when you fast track a project?

Options

  • AResources
  • BCosts
  • CCommunication
  • DRisks

Topics

#Fast tracking#Schedule compression#Project risk#Schedule risk

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions