PMIPMI
PMI-RMP · Question #84
PMI-RMP Question #84: Real Exam Question with Answer & Explanation
The correct answer is D: Risks. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
Your organization has a project that is expected to last 20 months but the customer would really like the project completed in 18 months. You have worked on similar projects in the past and believe that you could fast track the project and reach the 18 month deadline. What increases when you fast track a project?
Options
- AResources
- BCosts
- CCommunication
- DRisks
Topics
#Fast tracking#Schedule compression#Project risk#Schedule risk
Community Discussion
No community discussion yet for this question.