PMI-RMP · Question #85
Yolanda is the project manager of a high-profile project for her organization. This project has 124 stakeholders from across the organization and many of the stakeholders have high demands and…
The correct answer is A. Change log. The change log is the correct answer in this context because it records all change requests, including those arising from identified risks, and tracks their status and impact. It provides a documented history of risk-driven changes that must be communicated to stakeholders. The…
Question
Yolanda is the project manager of a high-profile project for her organization. This project has 124 stakeholders from across the organization and many of the stakeholders have high demands and expectations for the project. Yolanda will need several pieces of project information as she begins to communicate and manage the stakeholder expectations. Which of the following inputs of the manage stakeholder expectations process directly addresses the risks that could affect the project and which must be communicated to the project stakeholders?
Options
- AChange log
- BLow-level riskswatchlist
- CIssue log
- DStakeholder register
How the community answered
(19 responses)- A74% (14)
- B5% (1)
- C5% (1)
- D16% (3)
Explanation
The change log is the correct answer in this context because it records all change requests, including those arising from identified risks, and tracks their status and impact. It provides a documented history of risk-driven changes that must be communicated to stakeholders. The issue log (C) tracks problems that have already occurred, not future risks. The stakeholder register (D) captures stakeholder information but not risk details. The low-level risk watchlist (B) only covers minor risks below the threshold of active management and is not a formal standard PMBOK input to Manage Stakeholder Expectations.