PMIPMI
PMI-RMP · Question #85
PMI-RMP Question #85: Real Exam Question with Answer & Explanation
The correct answer is A: Change log. See the full explanation below for the reasoning.
Stakeholder Engagement
Question
Yolanda is the project manager of a high-profile project for her organization. This project has 124 stakeholders from across the organization and many of the stakeholders have high demands and expectations for the project. Yolanda will need several pieces of project information as she begins to communicate and manage the stakeholder expectations. Which of the following inputs of the manage stakeholder expectations process directly addresses the risks that could affect the project and which must be communicated to the project stakeholders?
Options
- AChange log
- BLow-level riskswatchlist
- CIssue log
- DStakeholder register
Topics
#Stakeholder Engagement#Project Documents#Change Management#Risk Communication
Community Discussion
No community discussion yet for this question.