PMI-RMP · Question #83
You work as a project manager for BlueWell Inc. You are working on a project and the management wants a rapid and cost-effective means for establishing priorities for planning risk responses in your p
The correct answer is B. Qualitative risk analysis. Qualitative Risk Analysis is specifically designed to be a rapid and cost-effective method for prioritizing risks by assessing their probability of occurrence and impact on project objectives. It produces a ranked list of risks that feeds directly into risk response planning. Qua
Question
You work as a project manager for BlueWell Inc. You are working on a project and the management wants a rapid and cost-effective means for establishing priorities for planning risk responses in your project. Which risk management process can satisfy management's objective for your project?
Options
- AHistorical information
- BQualitative risk analysis
- CQuantitative analysis
- DRolling wave planning
How the community answered
(41 responses)- A2% (1)
- B93% (38)
- C5% (2)
Explanation
Qualitative Risk Analysis is specifically designed to be a rapid and cost-effective method for prioritizing risks by assessing their probability of occurrence and impact on project objectives. It produces a ranked list of risks that feeds directly into risk response planning. Quantitative Risk Analysis (C) is more resource-intensive and numerically rigorous, making it less 'rapid and cost-effective' for general prioritization. Historical information (A) is an input, not a process. Rolling wave planning (D) is a scheduling technique, not a risk management process.
Topics
Community Discussion
No community discussion yet for this question.