nerdexam
PMIPMI

PMI-RMP · Question #83

PMI-RMP Question #83: Real Exam Question with Answer & Explanation

The correct answer is B: Qualitative risk analysis. See the full explanation below for the reasoning.

Perform Targeted Risk Analysis

Question

You work as a project manager for BlueWell Inc. You are working on a project and the management wants a rapid and cost-effective means for establishing priorities for planning risk responses in your project. Which risk management process can satisfy management's objective for your project?

Options

  • AHistorical information
  • BQualitative risk analysis
  • CQuantitative analysis
  • DRolling wave planning

Topics

#Qualitative Risk Analysis#Risk Prioritization#Risk Management Processes#Cost-effective Risk Management

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions