PMIPMI
PMI-RMP · Question #83
PMI-RMP Question #83: Real Exam Question with Answer & Explanation
The correct answer is B: Qualitative risk analysis. See the full explanation below for the reasoning.
Perform Targeted Risk Analysis
Question
You work as a project manager for BlueWell Inc. You are working on a project and the management wants a rapid and cost-effective means for establishing priorities for planning risk responses in your project. Which risk management process can satisfy management's objective for your project?
Options
- AHistorical information
- BQualitative risk analysis
- CQuantitative analysis
- DRolling wave planning
Topics
#Qualitative Risk Analysis#Risk Prioritization#Risk Management Processes#Cost-effective Risk Management
Community Discussion
No community discussion yet for this question.