nerdexam
PMIPMI

PMI-RMP · Question #82

PMI-RMP Question #82: Real Exam Question with Answer & Explanation

The correct answer is C: Add the identified risk to the risk register.. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

A project team member has just identified a new project risk. The risk event is determined to have significant impact but a low probability in the project. Should the risk event happen it'll cause the project to be delayed by three weeks, which will cause new risk in the project. What should the project manager do with the risk event?

Options

  • AAdd the identified risk to a quality control management control chart.
  • BAdd the identified risk to the issues log.
  • CAdd the identified risk to the risk register.
  • DAdd the identified risk to the low-level riskwatchlist.

Topics

#Risk identification#Risk register#Risk documentation#Project risk management process

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions