nerdexam
PMI

PMI-RMP · Question #645

A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project. What should the risk

The correct answer is B. Perform qualitative analysis.. Before assessing which risk has the greatest cost impact, the risk manager must first perform qualitative analysis to prioritize and screen the identified risks.

Perform Targeted Risk Analysis

Question

A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project. What should the risk manager do first to understand the impact on project cost?

Options

  • AConduct a subject matter expert (SME) meeting.
  • BPerform qualitative analysis.
  • CPrioritize after quantitative analysis
  • DPrioritize the stakeholders affected.

How the community answered

(43 responses)
  • A
    9% (4)
  • B
    77% (33)
  • C
    2% (1)
  • D
    12% (5)

Why each option

Before assessing which risk has the greatest cost impact, the risk manager must first perform qualitative analysis to prioritize and screen the identified risks.

AConduct a subject matter expert (SME) meeting.

An SME meeting may support qualitative or quantitative analysis as a technique, but it is not the first distinct process step in the risk management framework for assessing cost impact.

BPerform qualitative analysis.Correct

Qualitative risk analysis is performed before quantitative analysis in the standard risk management process, using probability and impact assessments to prioritize risks and determine which ones warrant further quantitative analysis. Performing qualitative analysis first ensures that resources for quantitative cost modeling are focused on the most significant risks, providing an efficient and structured path to understanding cost impact.

CPrioritize after quantitative analysis

Quantitative analysis follows qualitative analysis in the risk management process; proceeding directly to quantitative analysis skips the required qualitative screening step and misallocates resources.

DPrioritize the stakeholders affected.

Prioritizing stakeholders affected is a stakeholder management activity, not a risk analysis technique for assessing cost impact.

Concept tested: Qualitative risk analysis as prerequisite to quantitative cost analysis

Source: https://www.pmi.org/pmbok-guide-standards/practice-guides/risk

Topics

#Qualitative risk analysis#Risk prioritization#Risk analysis process#Cost impact assessment

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice