nerdexam
PMIPMI

PMI-RMP · Question #644

PMI-RMP Question #644: Real Exam Question with Answer & Explanation

The correct answer is A: Check the schedule for constraints. See the full explanation below for the reasoning.

Perform Targeted Risk Analysis

Question

The risk manager loaded the risk register, built the risks into the simul-ation software, and ran the Monte Carlo analysis. The P80 and P90 end dates are the same as the deterministic date. What should be the risk manager's next step?

Options

  • ACheck the schedule for constraints
  • BUse the P90 date on the risk report
  • CDecrease the number of iterations
  • DDecrease the risk consequences

Topics

#Monte Carlo Analysis#Schedule Risk Analysis#Schedule Constraints#Simulation Output Interpretation

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions