PMI-RMP · Question #643
During a project meeting, the project sponsor asks to close a project risk. The team does not recommend closing the risk because it is expected to be present in the next phase of the project work…
The correct answer is C. Compare the actual data with the risk baseline. When a sponsor requests closing a risk that the team believes will persist, the risk manager should compare current data against the risk baseline to objectively support or refute the closure decision.
Question
During a project meeting, the project sponsor asks to close a project risk. The team does not recommend closing the risk because it is expected to be present in the next phase of the project work. How should the risk manager address this concern?
Options
- ACompare the actual data with the historical data.
- BCompare the actual data with the subject matter expert (SME) criteria.
- CCompare the actual data with the risk baseline.
- DCompare the actual data with the project sponsor's expectation.
How the community answered
(47 responses)- A15% (7)
- B4% (2)
- C74% (35)
- D6% (3)
Why each option
When a sponsor requests closing a risk that the team believes will persist, the risk manager should compare current data against the risk baseline to objectively support or refute the closure decision.
Comparing actual data with historical data may provide general context but does not supply the project-specific thresholds and criteria needed to justify keeping a current risk open.
SME criteria can be subjective and situational; the risk baseline is the formally agreed-upon benchmark for evaluating risk status decisions.
The risk baseline documents the agreed-upon thresholds, criteria, and expected risk behavior established at the start of the project or phase. Comparing actual data against this baseline provides objective, documented evidence to determine whether the conditions for risk closure have been met, giving the risk manager a defensible basis for disagreeing with the sponsor's request.
Basing the decision on the project sponsor's expectation introduces bias and bypasses the objective, documented risk management process established for the project.
Concept tested: Risk baseline use in risk closure decisions
Source: https://www.pmi.org/pmbok-guide-standards/practice-guides/risk
Topics
Community Discussion
No community discussion yet for this question.