nerdexam
PMIPMI

PMI-RMP · Question #646

PMI-RMP Question #646: Real Exam Question with Answer & Explanation

The correct answer is A: Execute the risk response plan defined for the risk.. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

A project team working on a large software deployment project for a few months has been able to prevent a technical risk from occurring. However, an incident took place and triggered the technical issue. What should the risk manager do?

Options

  • AExecute the risk response plan defined for the risk.
  • BPostpone the software launch to sort out the technical issue.
  • CAssess the impacts and define the response actions with the subject matter experts (SMEs).
  • DMeet with the project manager to revisit the project schedule.

Topics

#Risk response execution#Risk monitoring#Issue management#Contingency planning

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions