nerdexam
PMI

PMI-RMP · Question #646

A project team working on a large software deployment project for a few months has been able to prevent a technical risk from occurring. However, an incident took place and triggered the technical iss

The correct answer is A. Execute the risk response plan defined for the risk.. When a risk that was being actively mitigated is triggered by an incident, the correct immediate action is to execute the pre-defined risk response plan.

Risk Monitoring and Reporting

Question

A project team working on a large software deployment project for a few months has been able to prevent a technical risk from occurring. However, an incident took place and triggered the technical issue. What should the risk manager do?

Options

  • AExecute the risk response plan defined for the risk.
  • BPostpone the software launch to sort out the technical issue.
  • CAssess the impacts and define the response actions with the subject matter experts (SMEs).
  • DMeet with the project manager to revisit the project schedule.

How the community answered

(35 responses)
  • A
    80% (28)
  • B
    6% (2)
  • C
    11% (4)
  • D
    3% (1)

Why each option

When a risk that was being actively mitigated is triggered by an incident, the correct immediate action is to execute the pre-defined risk response plan.

AExecute the risk response plan defined for the risk.Correct

A risk response plan was already developed and approved for this technical risk during planning; executing this pre-defined plan is the appropriate response when the risk event occurs, ensuring the team follows documented and agreed-upon procedures rather than improvising under pressure. Executing the plan promptly minimizes further impact and keeps the response controlled and traceable.

BPostpone the software launch to sort out the technical issue.

Postponing the launch is a business decision that may or may not be specified within the response plan, but deciding it ad hoc outside the established risk response process bypasses the approved approach.

CAssess the impacts and define the response actions with the subject matter experts (SMEs).

Assessing impacts and defining new response actions with SMEs is appropriate when no response plan exists; since a plan is already in place, this causes unnecessary delay in controlling the risk.

DMeet with the project manager to revisit the project schedule.

Revisiting the project schedule with the project manager is a downstream activity that may follow response execution, but it is not the immediate first step when a risk event has already been triggered.

Concept tested: Risk response plan execution upon risk trigger

Source: https://www.pmi.org/pmbok-guide-standards/practice-guides/risk

Topics

#Risk response execution#Risk monitoring#Issue management#Contingency planning

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice