PMIPMI
PMI-RMP · Question #646
PMI-RMP Question #646: Real Exam Question with Answer & Explanation
The correct answer is A: Execute the risk response plan defined for the risk.. See the full explanation below for the reasoning.
Risk Monitoring and Reporting
Question
A project team working on a large software deployment project for a few months has been able to prevent a technical risk from occurring. However, an incident took place and triggered the technical issue. What should the risk manager do?
Options
- AExecute the risk response plan defined for the risk.
- BPostpone the software launch to sort out the technical issue.
- CAssess the impacts and define the response actions with the subject matter experts (SMEs).
- DMeet with the project manager to revisit the project schedule.
Topics
#Risk response execution#Risk monitoring#Issue management#Contingency planning
Community Discussion
No community discussion yet for this question.