nerdexam
PMI

PMI-RMP · Question #606

An organization with a portfolio of unique business functions kicks-off a performance improvement project across the entire organization. There are a large number of stakeholders the project team will

The correct answer is A. Develop checklists based on historical information: Checklists are valuable tools in risk B. Conduct interviews, meetings, and focus groups: These are key methods for gathering D. Employ brainstorming to generate spontaneous ideas: Brainstorming is an effective technique. Risk identification relies on structured elicitation and creative techniques. (A) Developing checklists from historical information leverages lessons learned from similar past projects, ensuring known risk categories aren't overlooked. (B) Interviews, meetings, and focus groups g

Risk Process Facilitation

Question

An organization with a portfolio of unique business functions kicks-off a performance improvement project across the entire organization. There are a large number of stakeholders the project team will need to consider during risk identification. What three actions should the risk manager ensure the project team performs during risk identification? (Choose 3)

Options

  • ADevelop checklists based on historical information: Checklists are valuable tools in risk
  • BConduct interviews, meetings, and focus groups: These are key methods for gathering
  • CAssign a different risk manager for each portfolio unit
  • DEmploy brainstorming to generate spontaneous ideas: Brainstorming is an effective technique
  • EPerform qualitative and quantitative risk analyses

How the community answered

(29 responses)
  • A
    83% (24)
  • C
    7% (2)
  • E
    10% (3)

Explanation

Risk identification relies on structured elicitation and creative techniques. (A) Developing checklists from historical information leverages lessons learned from similar past projects, ensuring known risk categories aren't overlooked. (B) Interviews, meetings, and focus groups gather direct input from diverse stakeholders - critical when a large number of stakeholders are involved across unique business units. (D) Brainstorming encourages open, spontaneous idea generation, surfacing risks that structured methods might miss. Option C (assigning a separate risk manager per unit) is an organizational decision, not a risk identification action. Option E (qualitative/quantitative analyses) belongs to the risk analysis phase, which comes after identification.

Topics

#Risk Identification#Risk Management Process#Tools and Techniques#Stakeholder Input

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice