PMI-RMP · Question #605
A project is in the execution phase and involves large volumes of supplies. The project is the last phase of a 10-year initiative. The project sponsor asks the project manager to provide the performan
The correct answer is C. Variance Analysis. Variance analysis is a method used to compare planned project performance against actual performance. Since the project sponsor has requested a performance report for the entire 10- year initiative, variance analysis would allow the risk manager to identify discrepancies between
Question
A project is in the execution phase and involves large volumes of supplies. The project is the last phase of a 10-year initiative. The project sponsor asks the project manager to provide the performance report for the whole initiative. Which analysis should the risk manager do to provide the project manager with the performance report?
Options
- ATime Series Analysis
- BRegression Analysis
- CVariance Analysis
- DMonte Carlo Analysis
How the community answered
(57 responses)- A7% (4)
- B12% (7)
- C77% (44)
- D4% (2)
Explanation
Variance analysis is a method used to compare planned project performance against actual performance. Since the project sponsor has requested a performance report for the entire 10- year initiative, variance analysis would allow the risk manager to identify discrepancies between what was planned and what has been achieved over the course of the project. This analysis is crucial for understanding performance trends, cost deviations, schedule variations, and overall PMI's guidelines support the use of variance analysis in performance reporting as it provides insights into how well the project is adhering to its planned budget, schedule, and scope.
Topics
Community Discussion
No community discussion yet for this question.