PMI-RMP · Question #607
PMI-RMP Question #607: Real Exam Question with Answer & Explanation
The correct answer is A: A request to increase project earnings. The risk manager's request to include Field 2 in the scope of the current project is a clear attempt to increase the project's profitability by expanding its scope to a more lucrative area. This type of request is aimed at increasing project earnings, as it involves altering the
Question
A company has a project whose objective is to extract gold reserves from Field. However, another field closest to the company. Field 2, which has a higher probability of having twice as much gold reserves than Field. The risk manager requests the board of Directors to include Field 2 under the scope of the current project by management of change because the project's profitability will increase by 80%. What type of request is the risk manager describing?
Options
- AA request to increase project earnings
- BA request to increase project resources
- CA challenge to stakeholder thresholds
- DA challenge to the project investment
Explanation
The risk manager's request to include Field 2 in the scope of the current project is a clear attempt to increase the project's profitability by expanding its scope to a more lucrative area. This type of request is aimed at increasing project earnings, as it involves altering the project's objectives to capture a more significant financial opportunity. According to PMI, requests that seek to modify project scope for financial gain are typically categorized as efforts to increase project earnings or revenue.
Topics
Community Discussion