PMI-RMP · Question #557

PMI-RMP Question #557: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #557. The question stem and answer options stay visible for context.

Risk Strategy and Planning

Question

While executing an oil extraction project in an environmentally sensitive area, weather is the main cause of delay in the project work. The risk manager was aware that the delays caused by the weather could not be avoided or mitigated. What should the risk manager do to manage this risk?

Options

  • APerform time recovery actions.
  • BExecute the prevention plans.
  • CExecute the contingency plans.
  • DPerform change management.

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk response strategies#Contingency planning#Unavoidable risks#Risk execution