nerdexam
PMIPMI

PMI-RMP · Question #558

PMI-RMP Question #558: Real Exam Question with Answer & Explanation

The correct answer is A: Engaging the key stakeholders during the prioritization process. Risk prioritization is the process of assigning a level of importance to each identified risk based on its probability and impact, as well as other factors such as urgency, stakeholder tolerance, and project objectives. Risk prioritization helps the project team to focus on the m

Stakeholder Engagement

Question

After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a 2-week delay in the project. How could the risk manager have avoided the board's response?

Options

  • AEngaging the key stakeholders during the prioritization process
  • BPrioritizing the risks based on the project sponsor's risk appetite
  • CEngaging with the project sponsor before presenting to the board
  • DWorking with an established industry standard prioritization method

Explanation

Risk prioritization is the process of assigning a level of importance to each identified risk based on its probability and impact, as well as other factors such as urgency, stakeholder tolerance, and project objectives. Risk prioritization helps the project team to focus on the most significant risks and allocate resources accordingly. One of the tools and techniques for risk prioritization is stakeholder engagement, which involves involving the key stakeholders in the risk analysis and decision making process. Stakeholder engagement helps to ensure that the risk prioritization reflects the expectations and preferences of the stakeholders, and that they are aware of and agree with the results. By engaging the key stakeholders during the prioritization process, the risk manager could have avoided the board's request to sort the risks differently, as the board would have been part of the process and would have accepted the outcome.

Topics

#Stakeholder engagement#Risk prioritization#Communication planning#Project governance

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions