nerdexam
PMIPMI

PMI-RMP · Question #559

PMI-RMP Question #559: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #559. The question stem and answer options stay visible for context.

Risk Monitoring and Reporting

Question

A core project team is working on unrelated tasks in advance to reduce the risk of delay due to an external team not completing its tasks on time. The core project team has completed all possible unrelated tasks but cannot move forward, because the external team's tasks have yet to be completed. What should the risk manager do next?

Options

  • AStart a quantitative analysis to understand the impact.
  • BCrash the schedule to mitigate the risk consequences.
  • CTransfer the risk to the external team.
  • DAsk the risk owners to review the risk response plan.

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk monitoring#Risk response effectiveness#Risk owners#Corrective action
Full PMI-RMP PracticeBrowse All PMI-RMP Questions