PMI-RMP · Question #556
PMI-RMP Question #556: Real Exam Question with Answer & Explanation
The correct answer is C: The full risk description. The full risk description is the first thing that the risk manager should complete before moving forward with the risk response planning. The full risk description is a detailed statement that describes the risk, its causes, its effects, and its context. It provides the basis for
Question
A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning. What should the risk manager complete first?
Options
- AThe risk categorization
- BThe risk simul-ation
- CThe full risk description
- DThe risk response plan
Explanation
The full risk description is the first thing that the risk manager should complete before moving forward with the risk response planning. The full risk description is a detailed statement that describes the risk, its causes, its effects, and its context. It provides the basis for the risk analysis and the risk response planning. The risk categorization, the risk simul-ation, and the risk response plan are possible steps that the risk manager may take after completing the full risk description, but they are not the first thing to do.
Topics
Community Discussion
No community discussion yet for this question.