PMIPMI
PMI-RMP · Question #552
PMI-RMP Question #552: Real Exam Question with Answer & Explanation
The correct answer is C: Decision tree analysis. See the full explanation below for the reasoning.
Perform Targeted Risk Analysis
Question
A project team identified some risks in a project. Team members became interested in predicting the outcomes of their potential choices following their probability of occurrence. Which technique should the risk manager use?
Options
- APolitical, economic, social, technological, legal, and environmental (PESTLE) analysis
- BStrengths, weaknesses, opportunities, and threats (SWOT) analysis
- CDecision tree analysis
- DCost-benefit analysis
Topics
#Decision Tree Analysis#Quantitative Risk Analysis#Risk Analysis Techniques#Decision Making Under Uncertainty
Community Discussion
No community discussion yet for this question.