nerdexam
PMI

PMI-RMP · Question #553

In a large industrial business, an on-going system development project faces a previously identified risk. The risk is adequately managed by the risk manager, however there is still residual risk. Wha

The correct answer is C. Ask a subject matter expert (SME) to assess the residual risk and take action.. Residual risk is the risk that remains after planned risk responses have been implemented. Even when a risk is 'adequately managed,' residual risk may still require further action. Asking an SME to assess the residual risk (C) ensures that someone with specialized knowledge evalu

Perform Targeted Risk Analysis

Question

In a large industrial business, an on-going system development project faces a previously identified risk. The risk is adequately managed by the risk manager, however there is still residual risk. What should the risk manager do?

Options

  • AUpdate the risk register accordingly and review it in regular project meetings.
  • BAccept the risk because residual risks are often low.
  • CAsk a subject matter expert (SME) to assess the residual risk and take action.
  • DAssign a risk owner and set it as high priority and high impact.

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    85% (22)
  • D
    8% (2)

Explanation

Residual risk is the risk that remains after planned risk responses have been implemented. Even when a risk is 'adequately managed,' residual risk may still require further action. Asking an SME to assess the residual risk (C) ensures that someone with specialized knowledge evaluates whether the remaining risk level is truly acceptable or requires additional treatment. Option A (update the register and review in meetings) is passive and doesn't actively evaluate the residual risk. Option B (accept because residual risks are often low) is incorrect-residual risks must be assessed, not assumed to be low. Option D (assign a high-priority owner) is premature without first assessing the nature and magnitude of the residual risk.

Topics

#Residual risk#Risk reassessment#Risk response execution#SME engagement

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice