PMI-RMP · Question #478

A new risk manager is assigned to an ongoing project, what should the new risk manager do first to assess the project environment?

The correct answer is C. Review the policies and practices that are outlined in the risk management plan.. The risk management plan is the foundational document that defines how risk management is to be conducted on the project - including roles, responsibilities, risk thresholds, tools, timing, and reporting. Reviewing it first (C) gives the new risk manager an immediate understandin

Risk Strategy and Planning

Question

A new risk manager is assigned to an ongoing project, what should the new risk manager do first to assess the project environment?

Options

  • AReview potential next steps with the project team.
  • BReview the scope of work to determine the prescribed project methodology.
  • CReview the policies and practices that are outlined in the risk management plan.
  • DReview the contract and determine the resources and project funding.

How the community answered

(40 responses)
  • A
    5% (2)
  • B
    13% (5)
  • C
    80% (32)
  • D
    3% (1)

Explanation

The risk management plan is the foundational document that defines how risk management is to be conducted on the project - including roles, responsibilities, risk thresholds, tools, timing, and reporting. Reviewing it first (C) gives the new risk manager an immediate understanding of the agreed-upon framework before taking any action. Option A (reviewing next steps with the team) is a collaborative discussion, but it is not grounded in documented project context. Option B (reviewing scope of work for methodology) is relevant but secondary - methodology comes from the risk management plan and project charter, not scope alone. Option D (reviewing the contract and resources) is useful for understanding constraints but does not establish the risk management framework the new manager is expected to operate within.

Topics

#Risk Management Plan#Onboarding Risk Manager#Project Environment Assessment#Risk Management Framework