PMI-RMP · Question #477
PMI-RMP Question #477: Real Exam Question with Answer & Explanation
The correct answer is B: Ensure project team members proactively identify risks throughout the project to plan for possible. Risk identification should be an ongoing process throughout the project lifecycle. Encouraging project team members to proactively identify risks allows for continuous risk management and the development of appropriate response strategies as new risks emerge. One of the tasks in
Question
A project manager is assigned to a new project and is told they need to develop the project's risk register. When should the project manager identify the project risks?
Options
- AIdentify risks only at the project's midpoint for the stakeholders to review them
- BEnsure project team members proactively identify risks throughout the project to plan for possible
- CIdentify risks at the beginning of the project because the risk posture will not change
- DDelegate risk identification to each team member and have them record the risks on separate risk
Explanation
Risk identification should be an ongoing process throughout the project lifecycle. Encouraging project team members to proactively identify risks allows for continuous risk management and the development of appropriate response strategies as new risks emerge. One of the tasks in the domain of Risk Identification is to ensure that project team members proactively identify risks throughout the project life cycle, using various tools and techniques, to enable planning for possible risk response strategies. Risk identification is an iterative process that should be performed regularly and frequently throughout the project, as new risks may emerge or existing risks may change due to internal or external factors. The project manager should involve the project team members and other relevant stakeholders in the risk identification process, as they may have different perspectives, expertise, and insights on the project risks. The project manager should not identify risks only at the project's midpoint for the stakeholders to review them, because that would be too late and ineffective to manage the risks that may have already occurred or escalated. The project manager should not identify risks at the beginning of the project because the risk posture will not change, because that would be unrealistic and imprudent to assume that the project environment and conditions will remain static and predictable. The project manager should not delegate risk identification to each team member and have them record the risks on separate risk registers for their areas, because that would create inconsistency, duplication, and fragmentation of the risk information, and prevent a holistic and integrated view of the project risks.