nerdexam
PMI

PMI-RMP · Question #477

A project manager is assigned to a new project and is told they need to develop the project's risk register. When should the project manager identify the project risks?

The correct answer is B. Ensure project team members proactively identify risks throughout the project to plan for possible. Risk identification is a continuous, iterative process that occurs throughout the entire project lifecycle, not just at a single point in time (B). New risks emerge as the project evolves, assumptions are validated or invalidated, and the environment changes. Option A (identifyin

Risk Monitoring and Reporting

Question

A project manager is assigned to a new project and is told they need to develop the project's risk register. When should the project manager identify the project risks?

Options

  • AIdentify risks only at the project's midpoint for the stakeholders to review them
  • BEnsure project team members proactively identify risks throughout the project to plan for possible
  • CIdentify risks at the beginning of the project because the risk posture will not change
  • DDelegate risk identification to each team member and have them record the risks on separate risk

How the community answered

(46 responses)
  • A
    4% (2)
  • B
    91% (42)
  • C
    2% (1)
  • D
    2% (1)

Explanation

Risk identification is a continuous, iterative process that occurs throughout the entire project lifecycle, not just at a single point in time (B). New risks emerge as the project evolves, assumptions are validated or invalidated, and the environment changes. Option A (identifying risks only at the midpoint) misses both early project risks and late-emerging ones, and limits stakeholder review to a single snapshot. Option C (identifying risks only at the beginning) is incorrect because the risk posture absolutely changes as the project progresses - risks emerge, materialize, or become obsolete over time. Option D (delegating to individuals on separate registers) fragments the risk information, making it impossible to manage holistically; all risks should feed into a centralized risk register.

Topics

#Risk identification#Continuous risk management#Team collaboration

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice