PMI-RMP · Question #476

An organization that spans across different countries undergoes a digital transformation project. The project manager has assigned a risk management team leader who is a risk management certified cand

The correct answer is C. Educate stakeholders on best practices to perform risk management.. In the early stages of a large, cross-border digital transformation project, the single most impactful action a risk management team leader can take is to educate stakeholders on risk management best practices (C). Without a shared understanding of risk management principles, the

Stakeholder Engagement

Question

An organization that spans across different countries undergoes a digital transformation project. The project manager has assigned a risk management team leader who is a risk management certified candidate in their domain. What should the risk management team leader do in the early stages of the project?

Options

  • AConduct qualitative risk analysis to prioritize potential risks.
  • BPlan a solid risk response plan and secure the necessary funding.
  • CEducate stakeholders on best practices to perform risk management.
  • DBenchmark to an organization which has executed a similar project,

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    9% (3)
  • C
    70% (23)
  • D
    18% (6)

Explanation

In the early stages of a large, cross-border digital transformation project, the single most impactful action a risk management team leader can take is to educate stakeholders on risk management best practices (C). Without a shared understanding of risk management principles, the risk management process will be inconsistent, misunderstood, or ignored across different countries and departments. Option A (qualitative risk analysis) comes after risk identification, not at the very start. Option B (planning risk responses and securing funding) is premature before risks are even identified and analyzed. Option D (benchmarking to a similar organization) is a useful technique but is not the first priority - stakeholder alignment and education must come first to ensure the entire team can participate effectively in the risk process.

Topics

#Early project stages#Stakeholder education#Risk management best practices#Risk awareness culture