The correct answer is D: Enhance. See the full explanation below for the reasoning.

Risk Process Facilitation

Question

Tracy is the project manager of the NLT Project for her company. The NLT Project is scheduled to last 14 months and has a budget at completion of $4,555,000. Tracy's organization will receive a bonus of $80,000 per day that the project is completed early up to $800,000. Tracy realizes that there are several opportunities within the project to save on time by crashing the project work. Crashing the project is what type of risk response?

Options

  • ATransference
  • BMitigation
  • CExploit
  • DEnhance

Topics

#Risk response strategies#Opportunities (Positive Risks)#Enhance strategy#Schedule compression