nerdexam
PMI

PMI-RMP · Question #257

Tom is the project manager for his organization. In his project he has recently finished the risk response planning. He tells his manager that he will now need to update the cost and schedule baseline

The correct answer is A. New or omitted work as part of a risk response can cause changes to. Risk response planning can add new activities or remove planned work, which changes the cost and schedule baselines that define the project's approved plan.

Risk Strategy and Planning

Question

Tom is the project manager for his organization. In his project he has recently finished the risk response planning. He tells his manager that he will now need to update the cost and schedule baselines. Why would the risk response planning cause Tom the need to update the cost and schedule baselines?

Options

  • ANew or omitted work as part of a risk response can cause changes to
  • BRisk responses protect the time and investment of the project.
  • CRisk responses may take time and money to implement.
  • DBaselines should not be updated, but refined through versions.

How the community answered

(57 responses)
  • A
    95% (54)
  • B
    2% (1)
  • D
    4% (2)

Why each option

Risk response planning can add new activities or remove planned work, which changes the cost and schedule baselines that define the project's approved plan.

ANew or omitted work as part of a risk response can cause changes toCorrect

When the team defines risk responses, they may add contingency activities, preventive actions, or workarounds that were not in the original plan, or they may remove activities rendered unnecessary by the response strategy. These additions or omissions constitute changes to the project's scope of work that must be reflected in updated cost and schedule baselines. The updated baselines then become the new authorized reference for measuring project performance.

BRisk responses protect the time and investment of the project.

Stating that risk responses protect time and investment is a general benefit, not the technical explanation for why baselines must be formally updated.

CRisk responses may take time and money to implement.

While implementing risk responses does consume time and money, the precise reason for baseline updates is the addition or omission of specific work activities, not just resource consumption.

DBaselines should not be updated, but refined through versions.

Project baselines are formal, change-controlled documents that must be revised when approved scope, cost, or schedule changes occur - they cannot simply be versioned without reflecting actual approved changes.

Concept tested: Impact of risk response planning on cost and schedule baselines

Topics

#Risk Response Planning#Baseline Management#Cost Impact#Schedule Impact

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice