PMIPMI
PMI-RMP · Question #257
PMI-RMP Question #257: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #257. The question stem and answer options stay visible for context.
Risk Strategy and Planning
Question
Tom is the project manager for his organization. In his project he has recently finished the risk response planning. He tells his manager that he will now need to update the cost and schedule baselines. Why would the risk response planning cause Tom the need to update the cost and schedule baselines?
Options
- ANew or omitted work as part of a risk response can cause changes to
- BRisk responses protect the time and investment of the project.
- CRisk responses may take time and money to implement.
- DBaselines should not be updated, but refined through versions.
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk Response Planning#Baseline Management#Cost Impact#Schedule Impact