PMIPMI
PMI-RMP · Question #256
PMI-RMP Question #256: Real Exam Question with Answer & Explanation
The correct answer is D: Establish definitions of the level of probability and impact of risk event. See the full explanation below for the reasoning.
Perform Targeted Risk Analysis
Question
Shelly is the project manager of the BUF project for her company. In this project Shelly needs to establish some rules to reduce the influence of risk bias during the qualitative risk analysis process. What method can Shelly take to best reduce the influence of risk bias?
Options
- AGroup stakeholders according to positive and negative stakeholders and then complete the
- BDetermine the risk root cause rather than the person identifying the risk events
- CEstablish risk boundaries
- DEstablish definitions of the level of probability and impact of risk event
Topics
#Qualitative risk analysis#Risk bias reduction#Probability and impact definition#Risk assessment objectivity
Community Discussion
No community discussion yet for this question.